Four fixed blocks, with hard caps, so an executive can find the decision in ninety seconds. Report only what moved since the last review.

From The Portfolio Scorecard Executives Actually Read, a Portfolio Mondays episode on Portfolio Intelligence. Watch on YouTube.
Pairs with the Stop, Defer, or Resequence Capacity Card and the Commitment Reset Card.

Scorecard header

Portfolio
Review date
Planning window
Portfolio lead
What changed since last review (one sentence)

1Capacity Truth

One bottleneck role first, not a blended average across the whole portfolio. If the reserve is not visible, it will get spent.

Bottleneck role
People in the role this window
Line FTE in window Person-weeks StatusReserve: Intact / At risk
Gross capacity
BAU, support, and incident reserveprotected, not a pool
Leave, training, and required admin
Net capacity for funded initiatives
Kept funded demand
Planned slack

2Commitment Health

Deltas since the last review only. Status is On track, Watch, or Reset Needed. Cap the active rows. Recently stopped or deferred items collapse to one line underneath, not full history.

Initiative Sponsor LoadFTE or person-weeks Status Current commitment Delta since last review
Closed, stopped, or deferred since last review (one line)

Silent Exceptions strip

Work or scope that showed up, but is not on the funded list. Flag peak-week impact, not just the window average.

Item Estimated loadinclude peak-week impact Source Disposition

3Top Cross-Portfolio Risks and Dependencies

Hard cap: three. Name the risk, the provider and the consumer, the trigger date, and the owner. Everything else stays in the backup log.

Risk or dependency Provider and consumer Trigger date ConfidenceHigh / Medium / Low Owner

4Decisions Needed Today

Hard cap: three. Each decision is a real choice, with the tradeoff named in one line, and a person who has to make the call. If a scorecard has no decision on it, it is not ready for the room.

Decision Tradeoff or cost Owner Call due

No percent-complete bars. No ticket counts. No activity log. Strictly one page. Report deltas since last review, never full history.

Worked example (fictional)

Illustrative fictional snapshot. Not a real organization. Same platform engineering portfolio, two weeks later, at the next monthly review.

PortfolioFictional IT Digital Portfolio
ReviewNext monthly review, two weeks later
WindowCurrent 12-week window
Portfolio leadPortfolio lead

What changed: Gateway cutover moved to Watch on a 5-day partner sandbox slip. One silent exception caught before it ate peak slack.

1 Capacity Truth

Bottleneck: Platform Engineering (6 platform engineers).

Line FTE in window Person-weeks Status
Gross capacity (6 platform engineers)6.072Fixed for window
BAU, support, and incident reserve1.518Protected, intact
Leave, training, and required admin0.56Protected
Net capacity for funded initiatives4.048Baseline
Kept funded demand (3 active items)3.542Fits net
Planned slack0.56Guarded for peak cutover

Check: 6.0 minus 1.5 minus 0.5 = 4.0 net (48 person-weeks). Kept demand: 1.5 + 1.0 + 1.0 = 3.5 FTE (42 person-weeks). Planned slack: 4.0 minus 3.5 = 0.5 FTE (6 person-weeks).

2 Commitment Health

Initiative Sponsor Load Status Current commitment Delta since last review
Identity platform hardeningIdentity lead1.5 FTEOn trackReconfirmed external assurance date holdsSchema freeze locked on time
Partner API gateway cutoverGateway sponsor1.0 FTEWatchReconfirmed cutover windowPartner sandbox sign-off slipped 5 days
Security patch windowSecurity lead1.0 FTEOn trackReconfirmed remediation window holdsNo change

Closed from the prior cycle: Customer self-serve portal rebuild withdrawn (1.5 FTE released, old dates cleared). Customer analytics lake upgrade deferred to the next window, pending a fresh capacity check (1.0 FTE released).

Silent Exceptions strip (1 flagged)

Item Estimated load and peak-week impact Source Disposition
Unapproved reporting connector added to gateway cutover scope 0.5 FTE x 6 peak cutover weeks = 3.0 person-weeks. 12-week average: 0.25 FTE, looks harmless. During the 6 peak weeks: eats 100 percent of the 0.5 FTE planned slack. Peak slack remaining: 0.0 FTE. Side email. No intake check. No sponsor sign-off. Decision 1: decline and route to next-window intake

3 Top Cross-Portfolio Risks and Dependencies

Risk or dependency Provider and consumer Trigger date Confidence Owner
Partner sandbox sign-off slip (5 days)External partner readiness to Partner API gateway cutoverEnd of this weekMediumGateway sponsor
Identity schema freeze handoffIdentity platform hardening to Partner API gateway cutoverLockedHighIdentity lead

4 Decisions Needed Today

Both decisions are due today.

Decision Tradeoff or cost Owner Call due
1. Decline the unapproved reporting connector from gateway scope and route it to next-window intake Reporting stakeholder waits for the next cycle. Keeps 0.5 FTE peak slack intact for the gateway cutover. Gateway sponsor and portfolio lead Today
2. Escalate partner sandbox sign-off this week. If the trigger date slips, hold the gateway cutover by two weeks. Do not pull platform engineers off identity hardening, and do not raid the protected 1.5 FTE BAU reserve. Downstream launch shifts two weeks if the trigger misses. Protects the identity assurance date and the 1.5 FTE BAU reserve. Executive sponsor Today

The scorecard does not pick a softer status, hide a slip, accept a silent exception, or make the tradeoff. The portfolio lead owns the page. Sponsors own the calls.

Optional: AI Evidence-Pack Prompt

Paste this with your latest capacity card, commitment reset card, dependency log, and project notes. AI drafts the four blocks and flags what moved. The portfolio lead edits it down to one honest page. Sponsors own the calls.

You are drafting a one-page portfolio scorecard for an executive review. Using the capacity card, commitment reset card, dependency log, and project notes pasted below, fill the four fixed blocks. Block 1, Capacity Truth: put the bottleneck role first and show gross capacity, the protected BAU and support reserve, leave and admin, net capacity for funded work, kept funded demand, planned slack, and whether the reserve is intact or at risk. Block 2, Commitment Health: list only what moved since the last review (On track, Watch, or Reset Needed), plus a Silent Exceptions strip for any work or scope in the updates that is not on the funded list, with estimated load and peak-week impact. Block 3, Top Cross-Portfolio Risks and Dependencies: cap at three, each with provider and consumer, trigger date, confidence, and owner. Block 4, Decisions Needed Today: cap at three, each a real choice with the tradeoff in one line, an owner, and a call due date. Do not add percent-complete bars, ticket counts, or an activity log. Do not pick a softer status, hide a slip, accept a silent exception, or make the tradeoff. The portfolio lead edits this to one honest page and owns every status. Sponsors own the calls.

[paste the latest capacity card, commitment reset card, dependency log, and project notes here]