One-Page Portfolio Scorecard
Four fixed blocks, with hard caps, so an executive can find the decision in ninety seconds. Report only what moved since the last review.
From The Portfolio Scorecard Executives Actually Read, a Portfolio Mondays episode on Portfolio Intelligence. Watch on YouTube.
Pairs with the Stop, Defer, or Resequence Capacity Card and the Commitment Reset Card.
Scorecard header
1Capacity Truth
One bottleneck role first, not a blended average across the whole portfolio. If the reserve is not visible, it will get spent.
| Line | FTE in window | Person-weeks | StatusReserve: Intact / At risk |
|---|---|---|---|
| Gross capacity | |||
| BAU, support, and incident reserveprotected, not a pool | |||
| Leave, training, and required admin | |||
| Net capacity for funded initiatives | |||
| Kept funded demand | |||
| Planned slack |
2Commitment Health
Deltas since the last review only. Status is On track, Watch, or Reset Needed. Cap the active rows. Recently stopped or deferred items collapse to one line underneath, not full history.
| Initiative | Sponsor | LoadFTE or person-weeks | Status | Current commitment | Delta since last review |
|---|---|---|---|---|---|
Silent Exceptions strip
Work or scope that showed up, but is not on the funded list. Flag peak-week impact, not just the window average.
| Item | Estimated loadinclude peak-week impact | Source | Disposition |
|---|---|---|---|
3Top Cross-Portfolio Risks and Dependencies
Hard cap: three. Name the risk, the provider and the consumer, the trigger date, and the owner. Everything else stays in the backup log.
| Risk or dependency | Provider and consumer | Trigger date | ConfidenceHigh / Medium / Low | Owner |
|---|---|---|---|---|
4Decisions Needed Today
Hard cap: three. Each decision is a real choice, with the tradeoff named in one line, and a person who has to make the call. If a scorecard has no decision on it, it is not ready for the room.
| Decision | Tradeoff or cost | Owner | Call due |
|---|---|---|---|
No percent-complete bars. No ticket counts. No activity log. Strictly one page. Report deltas since last review, never full history.
Worked example (fictional)
Illustrative fictional snapshot. Not a real organization. Same platform engineering portfolio, two weeks later, at the next monthly review.
What changed: Gateway cutover moved to Watch on a 5-day partner sandbox slip. One silent exception caught before it ate peak slack.
1 Capacity Truth
Bottleneck: Platform Engineering (6 platform engineers).
| Line | FTE in window | Person-weeks | Status |
|---|---|---|---|
| Gross capacity (6 platform engineers) | 6.0 | 72 | Fixed for window |
| BAU, support, and incident reserve | 1.5 | 18 | Protected, intact |
| Leave, training, and required admin | 0.5 | 6 | Protected |
| Net capacity for funded initiatives | 4.0 | 48 | Baseline |
| Kept funded demand (3 active items) | 3.5 | 42 | Fits net |
| Planned slack | 0.5 | 6 | Guarded for peak cutover |
Check: 6.0 minus 1.5 minus 0.5 = 4.0 net (48 person-weeks). Kept demand: 1.5 + 1.0 + 1.0 = 3.5 FTE (42 person-weeks). Planned slack: 4.0 minus 3.5 = 0.5 FTE (6 person-weeks).
2 Commitment Health
| Initiative | Sponsor | Load | Status | Current commitment | Delta since last review |
|---|---|---|---|---|---|
| Identity platform hardening | Identity lead | 1.5 FTE | On track | Reconfirmed external assurance date holds | Schema freeze locked on time |
| Partner API gateway cutover | Gateway sponsor | 1.0 FTE | Watch | Reconfirmed cutover window | Partner sandbox sign-off slipped 5 days |
| Security patch window | Security lead | 1.0 FTE | On track | Reconfirmed remediation window holds | No change |
Closed from the prior cycle: Customer self-serve portal rebuild withdrawn (1.5 FTE released, old dates cleared). Customer analytics lake upgrade deferred to the next window, pending a fresh capacity check (1.0 FTE released).
Silent Exceptions strip (1 flagged)
| Item | Estimated load and peak-week impact | Source | Disposition |
|---|---|---|---|
| Unapproved reporting connector added to gateway cutover scope | 0.5 FTE x 6 peak cutover weeks = 3.0 person-weeks. 12-week average: 0.25 FTE, looks harmless. During the 6 peak weeks: eats 100 percent of the 0.5 FTE planned slack. Peak slack remaining: 0.0 FTE. | Side email. No intake check. No sponsor sign-off. | Decision 1: decline and route to next-window intake |
3 Top Cross-Portfolio Risks and Dependencies
| Risk or dependency | Provider and consumer | Trigger date | Confidence | Owner |
|---|---|---|---|---|
| Partner sandbox sign-off slip (5 days) | External partner readiness to Partner API gateway cutover | End of this week | Medium | Gateway sponsor |
| Identity schema freeze handoff | Identity platform hardening to Partner API gateway cutover | Locked | High | Identity lead |
4 Decisions Needed Today
Both decisions are due today.
| Decision | Tradeoff or cost | Owner | Call due |
|---|---|---|---|
| 1. Decline the unapproved reporting connector from gateway scope and route it to next-window intake | Reporting stakeholder waits for the next cycle. Keeps 0.5 FTE peak slack intact for the gateway cutover. | Gateway sponsor and portfolio lead | Today |
| 2. Escalate partner sandbox sign-off this week. If the trigger date slips, hold the gateway cutover by two weeks. Do not pull platform engineers off identity hardening, and do not raid the protected 1.5 FTE BAU reserve. | Downstream launch shifts two weeks if the trigger misses. Protects the identity assurance date and the 1.5 FTE BAU reserve. | Executive sponsor | Today |
The scorecard does not pick a softer status, hide a slip, accept a silent exception, or make the tradeoff. The portfolio lead owns the page. Sponsors own the calls.
Optional: AI Evidence-Pack Prompt
Paste this with your latest capacity card, commitment reset card, dependency log, and project notes. AI drafts the four blocks and flags what moved. The portfolio lead edits it down to one honest page. Sponsors own the calls.
You are drafting a one-page portfolio scorecard for an executive review. Using the capacity card, commitment reset card, dependency log, and project notes pasted below, fill the four fixed blocks. Block 1, Capacity Truth: put the bottleneck role first and show gross capacity, the protected BAU and support reserve, leave and admin, net capacity for funded work, kept funded demand, planned slack, and whether the reserve is intact or at risk. Block 2, Commitment Health: list only what moved since the last review (On track, Watch, or Reset Needed), plus a Silent Exceptions strip for any work or scope in the updates that is not on the funded list, with estimated load and peak-week impact. Block 3, Top Cross-Portfolio Risks and Dependencies: cap at three, each with provider and consumer, trigger date, confidence, and owner. Block 4, Decisions Needed Today: cap at three, each a real choice with the tradeoff in one line, an owner, and a call due date. Do not add percent-complete bars, ticket counts, or an activity log. Do not pick a softer status, hide a slip, accept a silent exception, or make the tradeoff. The portfolio lead edits this to one honest page and owns every status. Sponsors own the calls. [paste the latest capacity card, commitment reset card, dependency log, and project notes here]
One-Page Portfolio Scorecard · scottpresley.net/tools/portfolio-scorecard · Portfolio Mondays on Portfolio Intelligence · AI drafts. Humans decide.